    Hi Gary,

    Many thanks for your message. In future I recommend either asking for 100% deposit in escrow initially, or ask for 50% up front, complete 50% of the work, then ask for the final 50% deposit to be paid in escrow for completing a milestone.

    Once work has been completed you can then submit an invoice for all funds to be released from escrow.

    Please let me know if I can help you with anything else.

    Comment actions Permalink
  • Jutta

    Hi,

    if you accepted his suggestion in the workstream, you're pretty set in stone to deliver this. but one thing I can recommend is have a look at his buyer history and payment history-it should give you some idea?

    0
    Comment actions Permalink
  • Gary

    Thanks for your reply, I did actually tell him I want payment for 3 milestones:

    1. 50% deposit
    2. 25% On completion (remaining 50% added to escrow here)
    3. 25% Held back until Bugs are fixed

    He agreed and paid the first 50% - seems like a nice chap,

    I normally ask for 100% upfront for smaller jobs - best to get money in escrow first.